The Wudongde Power Station Power Transmission to Guangdong and Guangxi UHVDC Multi-terminal VSC-HVDC Demonstration Project (referred to as the “Kunliulong DC Project”) is invested and constructed by China Southern Power Grid. It starts from Kunbei Converter Station in Yunnan and terminates at Liubei Converter Station in Guangxi and Longmen Converter Station in Guangdong. The project was commissioned and put into power transmission in December 2020. As the world’s first ±800kV UHVDC multi-terminal VSC-HVDC transmission project, it achieved 19 world firsts. The ±800kV fiber insulators of Shandong Peiport Electric Power Science & Technology Co., Ltd. have been successfully applied to the key equipment at Liubei Converter Station.